State Plan Reconductoring Project
|
The State Plan (Reconductoring) funded works under distribution system of SBPDCL for Suply of materials
|
& equipments for Re-Conductoring/ Re-Strenthening of existing HT (33 Kv & 11 Kv) Feeders & LT Lines |
with allied works in Rural areas of 9 Circles(earlier 7 circles) of South Bihar. |
|
Work/Scheme
|
Cost (INR) Cr..
|
Reconductoring/ Re-Strenthening of HT Feeders & LT Lines |
Estimated - 1418.08 Awarded – 1306.89 |
|
|
Physical progress of project as on August’19 :
|
|
Re-strengthening of Existing HT (33 KV & 11 KV) Feeders & LT Lines with Allied Works in 7 circles of SBPDCL, Patna
(Progress Report upto 01.09.2019)
|
Circle |
33 KV (in CKM) |
11 KV (in CKM) |
LT (in CKM) |
Total (in CKM) |
Scope |
Achievement | Balance |
Scope | Achievement |
Balance | Scope | Achievement |
Balance | Scope | Achievement |
Balance |
Bhagalpur |
107.4 | 27.7 | 79.8 | 2933 | 837 | 2096 | 1370 | 749 | 621 | 4410 | 1613 | 2797 |
Munger | 106.4 | 27.2 | 79.23 | 1603 | 699 | 904 | 2418 | 851 | 1567 | 4128 | 1577 | 2551 |
Nalanda |
46.4 | 4.7 | 41.7 | 730 | 500 | 230 | 646 | 357 | 289 | 1378 | 862 | 561 |
Patna | 117.9 | 43.3 | 74.6 | 1471 | 979 | 492 | 2702 | 665 | 2037 | 4291 | 1688 | 2603 |
Bhojpur |
3.8 | 3.8 | 0.0 | 1311 | 771 | 540 | 1536 | 519 | 1017 | 2851 | 1294 | 1558 |
Sasaram | 46.6 | 11.2 | 35.4 | 1089 | 406 | 683 | 2498 | 679 | 1818 | 3633 | 1097 | 2536 |
Gaya |
32.0 | 12.5 | 19.5 | 1819 | 790 | 1029 | 4707 | 585 | 4122 | 6558 | 1388 | 5170 |
Grand Total (SBPDCL) | 460 | 130 | 330 | 10956 | 4982 | 5930 | 15878 | 4406 | 11471 | 27250 | 9519 | 17732 |
|